Case study project comprised of two phases including steel frame and cladding to a workshop extension including 7 no. In Ground Vehicle Lift Cassettes and an extensive refurbishment of the existing showroom and front entrance area. Both phases were carried out to extremely tight timescales and included a new UKPN electrical mains service to cope with the additional electrical loadings. The first phase of the project was completed exactly on programme and the second phase was subject to an accelerated programme which ensured completion of the complete project four weeks ahead of programme.
Volkswagen / Marriott Motor Group
DCA Ipswich
£ 0.75m
Traditional Tender